Construction Status

CURRENT STATUS

Updated on August 27, 2018

3rd Floor Brickwork completed.

2nd Floor Plastering in progress.

Construction Status Video as on 20 May 2018

CONSTRUCTION PROGRESS

(in chronological order)

September 23, 2017 – Shifted all inventory to Temporary Jamat Khana
October 18, 2017 – Demolition of existing buildings completed
October 19, 2017 – Ground Breaking ceremony
October 21, 2017 – Borewell digging completed
October 22, 2017 – Foundation work started
January 31, 2018 – Foundation work completed. All GF pillars cast upto lintel level.
February 14, 2018 – Sump tank completed.
March 4, 2018 – Ground Floor Roof Casting.
April 1, 2018 – First Floor Roof Casting
April 30, 2018 – Second Floor Roof Casting
June 10, 2018 – Third Floor Roof Casting
July 28, 2018 – 2nd Floor Brickwork Completed, Plastering started
July 30, 2018 – 3rd Floor Brickwork started
August 27, 2018 – 3rd Floor Brickwork completed
September 16, 2018 – 4th Floor Roof Casting