Construction Status

CURRENT STATUS

Updated on December 20, 2018

90% Brickwork of Entire Building Completed
Internal Plastering of 3 Floors Completed
Flooring of 3 Halls Completed

IN PROGRESS:

Ground Floor Plastering
4th Floor Brickwork

TO START SOON (INSHA ALLAH):
External Plastering
Tiling of Namaz Hall walls
Windows of Namaz Hall

Construction Status Video as on 20 May 2018

CONSTRUCTION PROGRESS

(in chronological order)

September 23, 2017 – Shifted all inventory to Temporary Jamat Khana
October 18, 2017 – Demolition of existing buildings completed
October 19, 2017 – Ground Breaking ceremony
October 21, 2017 – Borewell digging completed
October 22, 2017 – Foundation work started
January 31, 2018 – Foundation work completed. All GF pillars cast upto lintel level.
February 14, 2018 – Sump tank completed.
March 4, 2018 – Ground Floor Roof Casting.
April 1, 2018 – First Floor Roof Casting
April 30, 2018 – Second Floor Roof Casting
June 10, 2018 – Third Floor Roof Casting
July 28, 2018 – 2nd Floor Brickwork Completed, Plastering started
July 30, 2018 – 3rd Floor Brickwork started
August 27, 2018 – 3rd Floor Brickwork completed
September 16, 2018 – 4th Floor Roof Casting