Construction Status

CURRENT STATUS

Updated on June 10, 2018

3rd Floor Roof was cast on June 10.

1st Floor is now the prayer hall, although it is unfinished. 5-time prayers, Jumma and Taraveeh prayers are taking place in 1st Floor.

See walkthrough of Jamat Khana in the video below:

Construction Status Video as on 20 May 2018

CONSTRUCTION PROGRESS

(in chronological order)

September 23, 2017 – Shifted all inventory to Temporary Jamat Khana
October 18, 2017 – Demolition of existing buildings completed
October 19, 2017 – Ground Breaking ceremony
October 21, 2017 – Borewell digging completed
October 22, 2017 – Foundation work started
January 31, 2018 – Foundation work completed. All GF pillars cast upto lintel level.
February 14, 2018 – Sump tank completed.
March 4, 2018 – Ground Floor Roof Casting.
April 1, 2018 – First Floor Roof Casting
April 30, 2018 – Second Floor Roof Casting
June 10, 2018 – Third Floor Roof Casting
August 28, 2018 – 2nd Floor Brickwork Completed, Plastering started
August 30, 2018 – 3rd Floor Brickwork started